Press
DOM.RF: it has been decided who will develop the design concept of the cultural center in Petropavlovsk-Kamchatsky
061
This is the first urban comprehensive development plan in the Far East as part approved within the implementation
The BTS-MOST Group of Companies
Press
Gazprombank, DOM.RF and Bamtonnelstroy-Most Group began financing the construction of the Novobureysky overpass
064
The construction of an overpass will allow car drivers to cross a heavy-traffic railway line safely and
The BTS-MOST Group of Companies
Press
A section of the force main network was switched over within the construction of the road bridge over the Pregolya River in Kaliningrad
069
About 1,400 meters of a new pipeline were laid During the construction of the road bridge over the Pregolya
The BTS-MOST Group of Companies
Press
Workers began to paint the new Zeya Bridge in Blagoveshchensk
077
They will have to paint 210,000 square meters of surface Bamtonnelstroy-Most Group builders have proceeded
The BTS-MOST Group of Companies
Press
Specialists of Bamtonnelstroy-Most Group have started metro construction in Krasnoyarsk
079
There will be built 17.2 kilometers of underground structures of high-speed ground and underground light
The BTS-MOST Group of Companies
Press
Construction of a dam to protect the village of Vladimirovka from floods has started
085
Preparatory works are currently underway at the facility, the builders will procced to the main works
The BTS-MOST Group of Companies
Press
All piers of the bridge across the Oka River on M-12 Highway have been finished
037
23,800 cubic meters of concrete and 3,126 tons of reinforcement cage were used to build 17 piers Сoncreting
The BTS-MOST Group of Companies
Recent news
The final span segment of the bridge across the Oka River on M-12 Highway has been installed
032
Erection of bridge steel structures has been fully completed Deputy Prime Minister of the Russian Federation
The BTS-MOST Group of Companies
Press
Asphalt paving of the access roads to the new Zeya Bridge has begun
033
An asphalt manufacturing plant has been launched to produce asphalt The builders of Bamtonnelstroy-Most
The BTS-MOST Group of Companies
Press
Concreting of the new Zeya Bridge deck slab has been completed 
035
7,000 cubic meters of concrete and 2,500 tons of rebar were used for the slab construction The builders