General information
Beginning of works – January 2018.
Completion of works – 2021.
Total length of the railway sections – 454 km.
Due to its geographically scattered area, it is a unique and unprecedented project that involves reconstruction of 62 artificial structures located on the Korsakov-Arsentievka-Nogliki and Shakhty-Kholmsk sections.
January 2018
beginning of works
2021
completion of works
53 (21 + 31 + 1) + 9 bridges
total number of artificial structures

Construction
New bridges will be built:
- along the permanent bypass;
- along the existing axis with arrangement of the traffic on a temporary bridge and a bypass during the construction period.