Of the 900 builders of the Amur GPZ, 600 are residents of the Amur region

Recent news
The government of the Amur region held a seminar on this implementation of the agpz project.
Works on behalf of piles and preparation of the territory for the construction of a warehouse site with a hard surface.

As we have already reported, the government of the Amur region held a seminar with organizations involved in the implementation of the projects of the main gas pipeline “Power of Siberia” and the Amur gas processing Bureau “Gazprom” (the investor and customer of the project – “Gazprom pererabotka Blagoveshchensk”). O some important meeting details – in the topic extension. Representatives of enterprises of the Amur region presented their capabilities and received information about the needs for setting up materials, workers and services. The event was initiated by the Ministry of economic development of the Amur region.

Representatives of NIPIGAZ, which manages the construction of the Amur GPP, told about these project implementations, the current status of construction and installation works, as well as about the work carried out to attract contractors and suppliers to the latter in the quality of the region’s enterprises.

To date, seven contractors are involved in the construction of the Amur GPP facilities. B they are considered large construction companies of the Amur region. The USK Most company, which has a branch of SK “MOST-VOSTOK” in the city of Belogorsk, carries out work on the engineering preparation of the Amur GPP area (*- the work is performed by a subsidiary of LLC “Mostdorstroy” – approx. NARROW BRIDGE). Another Amur organization-CAP-holding-is involved in the operation of piles on the territory of construction of temporary buildings and structures, where a shift settlement of agpz builders will be built.

Road construction company of the Amur region “Asphalt” is expanding its work on the construction of access roads to the facilities of the Amur gas processing plant. The company already has the opportunity to work on projects within the initial stage of construction-it has completed work on the volume of two access roads to the site of the Amur gas processing plant with a total length of about ten kilometers. Now “Asphalt” is building roads to the railway station” Zavodskaya ” and to the construction site of a temporary pier on the river Zee. “Asphalt” performs a set of measures, including the development of the soil, the device and compaction of the land bed, the device of artificial structures, road construction and others. In addition, the local contractor has built in a Free residential home for employees of Niigata, building a second. Amur companies were involved in equipping the company’s offices in Blagoveshchensk and Svobodny with all the necessary equipment.

Today, more than 900 construction personnel are involved in the construction of the Amur GPP, about 600 of them are residents of the Amur region.

We visited the area the construction of the Amur gas processing plant. This is a huge amount, and it is impressive. This is about 400 individual vehicles that move around the site, this is the movement of soil. A huge number of people work, and among them there are companies from the Amur region that have entered and are teaching in projects on flat terms, having signed quite serious contracts. We can talk about the events of the Amur companies participating in the project. At the same time, we are not talking about small businesses that configure the product. I believe that this is quite a serious and tangible effect of such enterprises with the participation of the company managing the construction of the Amur gas processing plant, which we conducted in February this year. I hope that today’s event will be no less effective”,

– said the Minister of economic development of the Amur region Svetlana Balova.
Photo: press service of JSC “NIPIgaspererabotka”

Currently, the engineering preparation of the territory of the Amur gas processing plant is continuing-this is the development, interleaving and compaction of the soil, planning areas, strengthening slopes, and so on. 5 million cubic meters of soil have been developed and moved on the territory of the AGPP construction, and more than 1.1 million cubic meters of soil have been compacted. The excavation is carried out on a site of more than 2.3 million square meters, the area of the sections of the embankment device is currently equal to 551 thousand square meters. Ha bypass the process of testing soil under load. This is necessary for final approval of the type of piles that will be used in the construction of helium production facilities and cryogenic installations. Continuing the construction of access roads to the objects AGPZ. Construction of temporary buildings and structures (VSIs), including a shift settlement of builders, is underway. Work is continuing on preparing the territory for servicing railway infrastructure – Zavodskaya and Zavodskaya-2 stations, the railway track, and others. The preparation of territories for the construction of port hydro facilities on the Zee river has begun.

“We strive to tap the full potential of local third-party organizations, local service and product providers. Nipigaz employees have worked to collect information about the capabilities of enterprises in the Amur region engaged in road construction, production of equipment, construction materials, construction and installation work, providing transport services, services of design organizations, and others. Currently, the information obtained is analyzed using the specification of work performed in the framework of the Amur GPP construction project. It is important to note that the features of the project are material consumption and tight deadlines. Huge volumes require high rates of mobilization of construction personnel, maximum concentration of efforts of construction organizations, strict compliance with established deadlines, and high quality. NIPIGAZ, as a partner of Gazprom pererabotka Blagoveshchensk in the implementation of the project, will provide support to local businesses that are ready to cooperate with the announcement of proposals. However, we understand that the regions do not have all the necessary resources to implement a large-scale project. It is important for us to avoid problems of insufficient capacity. For this purpose, at various stages of construction, it is planned to attract engineering organizations and suppliers from other Russian regions. Also addresses the issue of attracting companies from other countries”,

– said the Deputy project Manager for the construction of the Amur gas processing plant Niigata Timur Sultanov.

During the seminars, Nipigaz employees explained to representatives of small and medium-sized businesses in the Amur region the procedure for participation in competitive procedures, qualification requirements for potential contractors, as well as conditions relating to the volume, quality and timing of work, and answered questions from Amur entrepreneurs.

Ha nipigaz website created a special section “Construction of the Amur GPP” ” here potential suppliers can get information about the competitions held and requirements for contractors. The site contains a list of competitive procedures, instructions on how to submit proposals, requirements for concluding contracts, and other information related to the implementation of the project. Tender procedures for selecting contractors and suppliers for the construction of the Amur gas processing plant are conducted on a specialized portal b2b.sibur.ru, where 190 enterprises of the Amur region registered in 2016.

The investor and customer of the construction project of the Amur gas processing plant-OOO Gazprom pererabotka Blagoveshchensk-is a member of the Group»Gazprom”. Construction is managed by NIPIGAZ, a leading Russian center for design, supply, logistics and construction management, which is part of the SIBUR Group.

The Amur gas processing plant will become the largest in Russia and one of the world’s largest natural gas processing plants. Its design capacity will be up to 42 billion cubic meters. M gas V God. The GPP will also include the world’s largest production of helium-up to 60 million cubic meters of m-v-god. To create the plant, the technology of the German company Linde will be used.