Current status of construction of a bridge over the Don river

Recent news
Construction of a railway bridge over the Don river as of the end of March 2018.

At the end of April 2018, it is planned to install a 2×77 m span raft, in connection with which work is underway on the device of a truss lift. The superstructure is assembled, reinforced, painted and moved to the rolling tracks.

Assembly is underway on the slipway of the 132m superstructure, 80% of the work has been completed. On July 1, 2018, it is planned to install the superstructure.

Work is underway to form a cone and embankment of the earthen bed on the left Bank of the don river.

Activities are underway to reconstruct the complex of buildings of the vohr. The opening of traffic on the bridge over the don river is planned for the end of 2018, and the work is being carried out in strict accordance with the schedule.