The first thousand meters of the excavation of metro station “Okskaya”

Recent news
TBM "Victoria" overcame the 1000-meter mark of the tunnel from the future Okskaya metro station to Stakhanovskaya metro station.

The Victoria tunnel shield passed the one thousand meter mark at night on may 23, which corresponds to the ring of reinforced concrete lining No. 556.

The first thousand meters of the tunnel was completed during the period December 2017-may 2018.

The total length of the distillation tunnel is 1993 linear meters. Working hours are 24 hours a day.

All tunneling works are carried out in accordance with the planned plan.

The speed of conducting tunneling works reaches 20 p.m. per day.

Sinking is carried out in conditions of dense urban development in the immediate vicinity of Ryazan Avenue, near buildings and structures and engineering communications.

The BTS-MOST Group of Companies