Eduard Davydov, the Director of the Construction Directorate of the USK MOST JSC, reported on the work progress. Up to date, the pile foundations of piers Nos. 6, 14, 19, 21, 22, 23, 24, 25 and 26 are completely ready. There are four drilling rigs operating at the site. Currently, the works on the installation of bored piles for several piers are in progress. Bridge piers No. 6 and No. 23 are completely ready.
“In general, for the moment, 9.1 thousand cubic meters of concrete have been poured in to form the piers. 311 thousand cubic meters were used to fill a road formation. The facility employs 83 units of machines and mechanisms, 80 units of auxiliary equipment and 739 personnel, ”
said Eduard Davydov.
At the meeting, it was noted that the construction of the facility is on schedule.
“We see that the works have been launched at all the sections and are being carried out efficiently; we continue monitoring the progress of the bidrge construction. This facility is critically important for us, so we are making every effort to complete the work on time,”
said the Governor of the Amur Region Vasily Orlov.