More Than 9,000 Cubic Meters of Concrete Were Laid in the Structure of the Bridge over the River Zeya

Recent news
Vasily Orlov was reported about the progress of the works

The Governor of the Amur Region Vasily Orlov held a meeting on the construction of the bridge across the Zeya.

“We continue to hear the reports on the process of works on the bridge weekly, the facility is under special control, it is strategically important for our region. We see that the builders cope with their job, the erection of the bridge is on schedule. In turn, the Government of the region provides all the necessary support ”,

– noted the Governor of the Amur Region Vasily Orlov.

“129 of 258 bored piles have been installed at the facility, the bodies and crossbars of the supports are being concreted, three supports # 6, 23, 24 are completely ready. The total volume of concrete placed in the structure was 9398 cubic meters. 1,350 tons of steelwork of the bridge’s superstructure were delivered to the construction site. Work is underway to build an embankment of the road formation, to set up a regulating dam, ”

said the project manager of the USK MOST JSC Eduard Davydov.

163 units of machines and mechanisms are involved in the construction of the facility, 752 people work hard. The construction of the bridge over the Zeya is on schedule.