The vehicular traffic is switched to a permanent scheme
The builders of Bamtonnelstroy-Most Group of Companies have mostly completed the construction of superstructures of the overpass located at the junction of the approaches to the new Zeya Bridge in Blagoveshchensk to the federal highway.
“In three months, we have installed 18 reinforced concrete beams of the superstructures with a length of 24 and 36 meters, connected them by constructing monolithic sections and finished painting. To carry out these works, the traffic was switched a temporary scheme, now, as the works are completed, we resume vehicular movement along the route familiar to residents,” Project Manager and Chief of the Zeya Branch Office of Bamtonnelstroy-Most JSC Eduard Davydov said.
After switching the traffic, the builders will begin to fill and construct exits from the overpass.
The construction of the new Zeya Bridge includes building 7 km of access roads, and the builders will also have to erect two transport interchanges: an overpass has been built at the junction with the federal highway, and an at-grade intersection will be built with the Vladimirovka-Zarechny Highway.